On June 11th 2013,slag mill project (90t/h) of Kazakhstan Standard Cement contracted by Sinoma Int. (Tianjin) passed performance tests with all parameters meeting guarantees. Kazakhstan Standard Cement and Sinoma Int. (Tianjin) then reached an agreement on the project handover and issuance of PAC. On June 25th this project was handed over to Kazakhstan Standard Cement.
On July 19th PAC was issued. This demonstrates that all milestones were achieved as per contract requirements for the project and the tests on completion were successfully concluded. This is a stage success for this slag mill project.